Our weekly meeting with the builder and project manager on Thursday, Feb. 22, was relatively short, so we don’t have a lot to report. We understand that we are very close to receiving the final plan approvals from the city of McKinney, which will allow construction to begin. The building plans and revisions submitted have been accepted by the city, but they are dependent on a small revision to the civil engineering plans being approved. That should be done by early next week.
Even if the city had approved the plans earlier, no work could have started this week due to the heavy rains we have received in north Texas. McKinney had around 6 inches of rain Tuesday and Wednesday, and a continuing cycle of storms is predicted for a few days.
Check back with us next Friday for the next update.